In That Quiet Earth, Off Hennur Road: Phases, Homes and Prices (October 2026)

By Propmonk Editorial Team·26 November 2026·5 min read
In That Quiet Earth (artist's impression)

In Bileshivale, a village reached from Hennur Road in North Bangalore, Total Environment In That Quiet Earth combines apartments with villas over 37 acres. Total Environment is delivering it phase by phase, and every phase carries a separate RERA number and finish date. Here we cover the buyer profile, the location, homes, prices, phases, approvals and pre-booking checks.

Key Facts

Karnataka RERA lists five registrations for the project. Its essentials:

  • Promoter: Total Environment Constructions Private Limited
  • Address: Bengaluru East taluk, Bidarahalli hobli, Bileshivale village, with the entrance from Avalahalli Main Road, a branch of Hennur Road
  • Site: 37 acres, built out in stages
  • Housing: nine towers of 2 BHK to 4 BHK flats, plus 55 villas
  • Water for the newer towers: BWSSB
  • Plan sanctioned by: Bruhat Bengaluru Mahanagara Palike (BBMP)
  • Entry ticket: Rs. 3.01 Crore (2 BHK)

Is It the Right Fit?

The project is made for families spending upward of Rs. 3 Crore who want a big home with its own garden. People working in Manyata Tech Park, or on the northern stretch of the Outer Ring Road also gain. It rewards those who put design and open space ahead of the cheapest rate per sq ft.

Anyone who must move quickly should consider the older towers or a resale flat. Budgets below Rs. 3 Crore, and buyers preferring a small block with few neighbours, are better served elsewhere in North Bangalore. Tower 8 and Tower 9 buyers face a wait of several years.

Setting and Commute

Bileshivale is a village on the eastern side of Hennur Road, within the pocket bounded by Kothanur, Hennur and Bagalur Road. Access is from Hennur Road via Avalahalli Main Road, inside the locality known as Off Hennur Road. Southward, Hennur Road joins the Outer Ring Road; northward, it runs to Bagalur and the airport.

The closest big office hub is Manyata Tech Park, roughly 6 km west as the crow flies. Next come the office parks near Nagavara and Hebbal on the ring road. Over the last ten years, Hennur Road has filled up with schools, hospitals and shops.

Namma Metro's airport Blue Line, being built on the ring road with stations planned from Hebbal to Nagavara, is beyond walking distance. Commuting relies on Hennur Road, so drive it at rush hour before deciding.

Layouts and Sizes

Buyers can choose a flat from 2 BHK to 4 BHK or a 4 BHK villa. Each tower is stepped, narrowing as it climbs, so flats open onto landscaped garden terraces. This private outdoor space sets them apart from an ordinary tower flat.

A 2 BHK flat measures 1,431 sq ft, and a 3 BHK either 2,305 or 2,628. The 4 BHK flat is 2,890 sq ft, while the villa, also 4 BHK, covers 3,430.

Only 3 BHK homes are offered in the two latest towers. RERA puts the carpet area near 2,565 sq ft for a Tower 8 flat and near 1,591 sq ft for a Tower 9 flat, with two parking bays each.

Prices and Purchase Costs

The cheapest flat, a 2 BHK, costs Rs. 3.01 Crore and the dearest, a 4 BHK, costs Rs. 6.07 Crore. Every plan works out close to Rs. 21,000 a sq ft.

Area (sq ft)PriceLayout
1,431Rs. 3.01 CroreFlat, 2 BHK
2,305Rs. 4.84 CroreFlat, 3 BHK
2,628Rs. 5.52 CroreFlat, 3 BHK
2,890Rs. 6.07 CroreFlat, 4 BHK
3,430On requestVilla, 4 BHK

Registration adds 2% and stamp duty 5.6% once cess and surcharge are included. Both together come near Rs. 22.88 Lakhs on the Rs. 3.01 Crore flat. GST is payable on any purchase made before the occupancy certificate, so make sure the cost sheet shows it.

For illustration, banks lend at most 75% of value once a loan passes Rs. 75 Lakhs, so a Rs. 3.01 Crore flat needs Rs. 75.25 Lakhs down (25%). Borrowing the rest at 8.5% for 20 years gives an EMI near Rs. 1.96 Lakhs monthly. Try other figures in the EMI calculator.

Phase-Wise Schedule

A home's phase fixes both its RERA number and its due date.

Due byRegistrationWhat it coversGranted
30 September 2026Towers 1 to 4 (In That Quiet Earth)Flats in four 35-storey towers19 May 2018
31 December 2026Phase 2A55 villas1 October 2020
1 May 2028Towers 5 to 7 (Phase 2B)324 flats, three 27-storey towers6 July 2022
31 March 2031Tower 9 (Phase 2C)120 flats, a single 29-storey tower6 April 2024
31 December 2032Tower 8120 flats, a single 29-storey tower31 January 2025

Both early registrations have had one extension each. The first phase was originally due on 31 December 2025 and now has 30 September 2026, while Phase 2A shifted to 31 December 2026, also from 31 December 2025. Buyers in these phases should check whether the tower or villa has its occupancy certificate yet.

Later towers run on long schedules, and the newest registration, Tower 8, is due only at the close of 2032. Get the planned handover for the exact tower in writing and set it against the registered date.

RERA Record and Approvals

The project holds RERA approval, and the latest tower registered, Tower 8, carries PRM/KA/RERA/1251/446/PR/310125/007467. The first phase and Phases 2A, 2B and 2C each have a separate number. Searching the state RERA website by phase and project name brings up any of them. Each record also holds the approved plan, quarterly progress and any complaints, and it is the quickest check on a home's carpet area and parking.

The Developer

Two architects founded Total Environment in Bangalore in 1996. The firm handles both design and construction itself, and its hallmarks are timber, bare brick and terrace gardens. Whitefield's Windmills of Your Mind is among its finished city projects.

The earlier towers here are the best guide to the later ones. A completed flat reveals how well the common areas are kept, how the terrace gardens have grown and how solidly it was built.

Pre-Booking Checklist

Cover these points before paying anything at this project.

  1. Pin down the home's phase and RERA number, then study that phase's record online
  2. Get the tower's handover date in writing, together with the agreement's delay clauses
  3. Ask to see the occupancy certificate for the villas and Towers 1 to 4
  4. Check the agreement's carpet area, terrace area and parking against RERA
  5. Request a cost sheet showing GST, parking, club fee, maintenance deposit and corpus fund
  6. Ask whether the seller is the developer (first sale) or a previous owner (resale)
  7. Have a lawyer go through the phase's title papers and Encumbrance Certificate

Frequently Asked Questions

Is In That Quiet Earth registered with RERA?+
Yes. Each of its five phases holds its own Karnataka RERA number. The newest, Tower 8, was registered on 31 January 2025 as PRM/KA/RERA/1251/446/PR/310125/007467.
How much do homes cost at In That Quiet Earth?+
The 2 BHK of 1,431 sq ft opens at Rs. 3.01 Crore, and the 4 BHK flat of 2,890 sq ft goes up to Rs. 6.07 Crore. That is close to Rs. 21,000 a sq ft.
Where is In That Quiet Earth located?+
It is in Bengaluru East taluk, Bidarahalli hobli, Bileshivale village, entered from Avalahalli Main Road, which branches off Hennur Road in North Bangalore.
When will each phase of In That Quiet Earth be completed?+
Registered deadlines: 30 September 2026 for Towers 1 to 4, 31 December 2026 for the villas, 1 May 2028 for Towers 5 to 7, 31 March 2031 for Tower 9 and 31 December 2032 for Tower 8.
How many towers are there at In That Quiet Earth?+
Nine towers are registered. Four rise 35 floors (Towers 1 to 4), three rise 27 floors (Towers 5 to 7) and two rise 29 floors (Tower 8, Tower 9), with 55 villas in Phase 2A.