Three White-Topped Mysore Roads Set to Reopen Ahead of Dasara 2026

Dasara visitors to Mysore should find three key city roads freshly concreted. Manandavadi Road, the Manipal Junction road and Banni Mantap Road are set to reopen by 5 October 2026. All three belong to a white-topping project worth Rs. 393.8 Crore, run by the Public Works Department, or PWD, which spans 12 major roads covering 46.088 km.
Three Stretches Near the Finish Line
Work on these roads started in April 2026 and has reached its last stage. Padmanabha, executive engineer at the PWD, stated on 28 September 2026 that the concreting would wrap up by 5 October, with traffic allowed in afterwards. This year Dasara falls between 11 and 21 October, when the city's roads see their peak traffic of the year.
Ahead of concreting, underground utilities on each road were moved to the side. Water supply, drainage, telecom and power lines were shifted, with the owning departments involved. This matters because a finished concrete road is expensive to dig up and fix.
Festival Pause for the Rest
The district administration has ordered a halt to the remaining white-topping during the festival. Pending work picks up again after the celebrations close on 21 October. Stretches that are paused or yet to be concreted include:
- Hunsur Road, Metropole Circle to its Hinkal end on the Outer Ring Road
- JLB Road, from Yelethota Junction to the city railway station
- KRS Road, Irwin Road and Mahadevapura Road
- Hardinge Circle to Kempegowda Circle
- Ramavilas Road's link to Banumaiah College Junction
- Vishwamanava Double Road and Zoo Road
- The Mini Vidhana Soudha connecting road, plus the Karnataka Police Academy corridor road
Living With White-Topping
Officials say the concrete should last around 20 years, ending the annual pothole cycle and improving drivers' view of the road. The technique puts a cement concrete layer on top of asphalt already in place, giving a tougher road that survives the monsoon with little patching. The price comes during the works: roads close fully or partly for months, traffic spills into side streets, and roadside shops lose access for a time.
The payoff is already visible where people living and trading along the first three roads get a completed surface in the busiest season after roughly six months of works. The remaining stretches face the same cycle when work resumes.
Buyer's Perspective
Concreting an arterial road genuinely helps the neighbourhoods along it, improving drainage and daily trips. The gain is modest, though: existing roads are being rebuilt without adding any lane or road, so the city's layout and distances do not change.
If you are eyeing a home off KRS Road, JLB Road or Hunsur Road, expect diversions and closures once work restarts after 21 October. Visiting during the works shows what access will be like. Whatever the road works, a Mysore purchase still rests on layout or building approval, clear title, RERA registration with Karnataka for new projects, and water supply.